Heathlands Park Project - The Paths

 

A few inches of top soil have been excavated for the entire width and length of the path between the Oxclose and Deepwell estates.

 

A central channel has been excavated for the ducting that will carry electrical cables.

 

View is from the Deepwell Estate.

 

Mini digger excavating the central channel in the path.

 

View is from the Oxclose Estate.

 

Hardcore material is placed on top of the ducting and compacted down.

 

View is from the Deepwell Estate.

 

Supporting edges of the path are laid.

 

Additional foundation material is compacted down on top of the hardcore.

 

View is from the Deepwell Estate.

 

A primary layer of Tarmac is layed down.

 

View is from the Deepwell Estate.

 

Finally an "A-Frame" is installed at the Oxclose Estate end of the path.

 

View is from the Oxclose Estate.

 

The construction of another path starts - linking Deepwell Court with Deepwell Mews.

 

Excavations start.

 

View is from Deepwell Mews.

 

Hardcore is layed down (not compacted yet).

 

View is from Deepwell Mews.

 

Tarmac is layed down.

 

View is from Deepwell Mews.

 

 

 

 